Beginning July 11, City of Thomasville contractors will begin placing asphalt pavement along several streets where sewer main replacements occurred. A schedule of work is listed below:
- Cecil Street - 10 days
- Friar Tuck Lane - 5 days
- Sherwood Drive - 5 days
- West Loomis Street - 5 days
There will be temporary lane closures while the work is underway; however, the roadways will remain open to local traffic. Travelers in the area are encouraged to select an alternate route or to prepare for potential traffic delays.
For more information about this project, please call the City of Thomasville’s Engineering Department at 229- 227-7009.